Sacramento Office: Rapid Mobilization & Full-Scope Environmental Remediation


Client:
Restoration Contractor
Service: Full-Scope Environmental Remediation
Location: Sacramento, CA


Project Overview

A restoration contractor contacted Alliance Environmental after their primary abatement provider was unable to manage the full scope of a large-scale environmental remediation project. The facility required remediation across approximately 10,000 sq. ft. along with complete duct cleaning throughout the building.

Alliance Environmental delivered a Rapid Order of Magnitude (ROM) estimate within eight hours and fully mobilized in under 24 hours, ensuring the project remained on schedule.


Project Scope & Execution

Initial Work

  • Wrapped and protected IT equipment and televisions
  • Handed off porous contents to a third-party cleaning vendor
  • Sealed cavities
  • Completed detailed HEPA vacuuming and wet wiping in the initial work area


Continued Remediation & Cleaning

  • Wrapped additional equipment and electronics for protection
  • Transferred remaining porous contents for off-site cleaning
  • Sealed additional cavities
  • Extended containment into the next work area
  • Sealed all critical barriers
  • Wiped and covered cabinets and appliances
  • Cleaned carpet and installed protective poly covering
  • Performed comprehensive decontamination: HEPA vacuuming and wet wiping of walls, ceilings, and floors following Lead-Safe work practices
  • Conducted a final internal walkthrough to confirm the area was ready for clearance testing


    Results

    • Completed the full scope within the required three-day window
    • Achieved clearance the following day
    • Due to strong performance and rapid response, Alliance Environmental is being considered to complete the remaining portion of the project